A two-year, two-phase project to rebuild the aging main runway at Redmond Municipal Airport is set to begin later this month, officials said Wednesday.

"We're simply at the point where the current runway was last overlaid, back in 1993, so by the time we finish up both phases it will be right around 23-24 years -- so right within the normal life-cycle for pavement," Airport Manager Jeff Tripp said Thursday.

There are no potholes or pits on the runway now, but Tripp says if it isn't upgraded, problems could pop up and cause a bumpy, unsafe ride for air travelers. "On a road, you can always put up some cold patch, put up a few signs and call it good,"Tripp said."You can't do that on a runway, so we need to make sure it's in top condition at all times." The first phase starts August 18th. It will take about 90 days and include reconstruction of 1,290 feet of runway, upgrading to new high-intensity lights and drainage improvements, just to name a few elements. Redoing the runway could mean rerouting airlines, so communication up in the sky has to be air-tight. "We'll be putting up what we call 'runway closure X's' -- big, large, lighted X's you can see for about 30 miles, to help warn pilots that the runway is closed," Tripp said. " In addition, we have what are called 'notices to airmen' that are published that all pilots are supposed to be checking before they take off and go to an airport,. The second phase of the project will start in the fall of 2015, consisting of full depth reconstruction of the remaining 5,750 feet of runway.

"Next year, in Phase 2, when we actually reach the intersection of both runways, we will have to actually close the airport for a period of time," Tripp said. "Right now, we are trying to minimize the closure to as little as possible. It could be a week, two weeks or three weeks, but right now we aren't sure."

The total cost of the two-phase project is estimated at about $20 million, with the Federal Aviation Administration picking up nearly 94 percent of the cost. The city hopes to receive a Connect Oregon V grant to offset the city's portion of the cost and expects to hear on that in September, officials said. Here's the full news release from the city:

As part of the City of Redmond's continuing commitment to provide the highest quality airport facilities and services to the Central Oregon region and its air travel needs, the Redmond Airport will begin a 90-day pavement rehabilitation project to the airport's primary runway (Runway 4-22) starting on Monday, August 18.

This capital improvement project is intended to help maintain and prolong the useful life of the airport's pavements.

Typically, asphalt pavements have a lifespan of approximately 20-30 years, depending upon local environmental conditions and pavement management practices. Runway 4-22 was last reconstructed in 1993; this project will extend the pavement life for an additional 20-year period.

The current project is comprised of two phases. Phase 1 is scheduled for completion in the fall of 2014 and consists of the following major project items:

1. Full depth reconstruction of approximately 1,290 feet of Runway 4-22; 2. Construction of precision approach markings and new runway designator numerals (4-22 to 5-23); 3. Construction of runway grooving; 4. Construction of runway drainage improvements; 5. Construction of new high-intensity runway lights; 6. Construction of runway shoulder and runway safety area grading; 7. Updating runway guidance signage and pavement markings associated with the runway designator change from "Runway 4-22" to "Runway 5-23"; 8. Updating runway guidance signage and pavement markings associated with the runway designator change from "Runway 10-28" to "Runway 11-29"; and 9. Reconfiguration of Taxiway "E" markings.

The project was designed by Century West Engineering of Bend. The construction contract for Phase 1 work, in the amount of over $2.633 million was awarded to High Desert Aggregate and Paving of Terrebonne through a competitive bid process.

Phase 2, scheduled for completion in the fall of 2015, will consist of full depth reconstruction of the remaining 5,750 feet of Runway 4-22, runway grooving, runway drainage improvements, high-intensity runway lights, and runway shoulder/runway safety area grading.

Project construction updates will be available on-line at www.flyrdm.com under the News & Media section.

The airport is sensitive to the impact this project may have on our neighbors. This runway closure will require the rerouting of all aircraft arrivals and departures to Runway 10-28 (northwest to southeast) for the duration of the project.

Redmond citizens may notice increased aircraft activity and noise over the city of Redmond while the primary runway is closed.

The airport will work with the airport traffic control tower and aircraft operators to minimize noise impacts to the greatest extent possible. Citizens may contact the Airport at 541-504-3499 or RDM@flyrdm.com to report noise disturbances.

The Redmond Municipal Airport (Roberts Field - RDM) is the aviation gateway to Central Oregon. Owned and operated by the City of Redmond, the airport offers a full range of general and commercial aviation services. RDM is served by four air carriers; Alaska Air, American Airlines, Delta Air Lines, and United with 15 daily direct flights to Denver, Los Angeles, Portland, San Francisco, Salt Lake City, and Seattle.

Recommended for you

(0) comments

Welcome to the discussion.

Keep it Clean. Please avoid obscene, vulgar, lewd, racist or sexually-oriented language.
PLEASE TURN OFF YOUR CAPS LOCK.
Don't Threaten. Threats of harming another person will not be tolerated.
Be Truthful. Don't knowingly lie about anyone or anything.
Be Nice. No racism, sexism or any sort of -ism that is degrading to another person.
Be Proactive. Use the 'Report' link on each comment to let us know of abusive posts.
Share with Us. We'd love to hear eyewitness accounts, the history behind an article.